Velocity / Throughput

The average amount of the backlog delivered during a sprint by the team. Used by the product team for planning. There is no such thing as good or bad velocity. This is commonly misunderstood to be a productivity metric. It is not.

What is the intended behavior?

After a team stabilizes, the standard deviation should be low. This will enable realistic planning of future deliverables based on relative complexity. Find ways to increase this over time by reducing waste, improving planning, and focusing on teamwork.

How to improve it

  • Reduce story size so they are easier to understand and more predictable.
  • Minimize hard dependencies. Each hard dependency reduces the odds of on-time delivery by 50%.
  • Swarm stories by decomposing them into tasks that can be executed in parallel so that the team is working as a unit to deliver faster.

How to game it

  • Cherry pick easy, low priority items.
  • Increase story points
  • Skip quality steps.
  • Prematurely sign-off work only to have defects reported later.

Guardrail Metrics

Metrics to use in combination with this metric to prevent unintended consequences.

  • Quality defect ratio goes up as more defects are reported.
  • WIP increases as teams start more work to look more busy.

References